ECR 2.0 Process Flow

After login into ECR 2.0 portal the employer will get the link for Payments in the menu bar.

Under payments he will have the following links at present:

a. ECR 2.0 Upload

b. Direct Challan Entry

c. View Challans

The link ECR 2.0 Upload allows to upload both the regular monthly return and the arrear ECR 2.0 file. The process is in the following five steps:

  • Upload
  •  Verify
  •  Prepare Challan
  •  Finalise Challan
  •  Pay

The process from upload till payment is as follows:

UPLOAD

The following information will be required at the time of uploading the ECR 2.0/Arrear  file:

  • Wage month: For selecting the wage month and year against which the file is to be uploaded.
  • Date of disbursement:
  • The file that has to be uploaded can be selected then.
  • File type: Select ECR 2.0 for the Regular Monthly file and Arrear for the Arrear payments.
  • Contribution rate: By default it will be 12%. If this is changed to 10% additional information has to be selected from the following:
    • Bidi
    • Brick
    • Coir
    • Jute
    • Guar Gum
    • Less than 20 employees
    • Sick Establishment permitted by EPFO Office

Remarks: This is for the help of the employers who are paying through multiple ECR for same month. Here they can add remarks to identify the particular ECR.

Download ECR and UAN related PDFs

Download UAN 2.0 & ECR 2.0 user manual, FAQs, Introduction, Process flow

VERIFY ECR STATEMENT

Once the data is uploaded, the software will validate for the file for the format and the other validations and if the validation fails, the error file will be created and the employer can then download the file, check error, rectify them and again upload the file. In case the validations are successful, the ECR 2.0 Statement file in PDF will be generated and the employer can download the same and after verifying the data can verify the same. He can also reject the file and again upload the correct file. The PDF will display the name as uploaded in the ECR and also the name as per the UAN Repository. In case the name is wrong the employer should get the same changed through the process explained on the epfindia website. The remitted amount will be credited against the UAN even if the name differs. The PDF will also display the benefit amount under the PMRPY and PMPRPY Schemes against the eligible employees and the benefit amount will not be added against the Challan amount to be paid. The payment of the benefit amount in the members account will be directly from the Government of India Fund.

PREPARE CHALLAN

Once the ECR 2.0 Statement has been verified, the said ECR 2.0 will appear for preparation of the challan under the header In Process ECRs. The employer still has the option to cancel the approved ECR Statement through the Cancel Button against the In Process ECRS. On click of the Prepare Challan, the Summary Sheet will open and the summary data based on the uploaded ECR 2.0 will be displayed.

Following additional data will have to be entered:

  • Total EDLI Contribution: The calculated data will be displayed but the employer can edit the same.
  • Total EPF Charges (A/c 2): There will be data fields for Administration and Inspection. In case the establishment is exempted under the EPF Scheme employer should enter against the Inspection (for the Inspection charges) and if the establishment is not exempted then he should enter the administrative charges against the Administration.
  • Total EDLI Charges: (A/c 22): There will be data fields for Administration and Inspection. In case the establishment is exempted under the EDLI Scheme employer should enter against the Inspection (for the Inspection charges) and if the establishment is not exempted then he should enter the administrative charges against the Administration.
  • Total number of Employees during the month:
  • Number of Excluded Employees:
  • Gross wages of Excluded Employees:

After entry of the data the employer can click the Generate Challan.

FINALISE CHALLAN

  • Once the challan is generated the same will be listed under the Draft Challan List where the employer can still edit the challan.
  • Edit of the generated challan means that the employer can only edit the data in the 6 fields that were entered by him while preparing the challan.
  •  If the ECR data is to be changed the employer will have to upload another ECR file with the correct data.
  •  If the data is correct the employer can finalise the challan.
  •  Once finalised the Challan will be listed for the online payment and a link for the PAY will appear under the head In-process challan list.
  •  The challan can be printed for record purpose as the payment has to be made online only.
  •  The challan will show the amount to be paid by the employer account wise and the benefit amount under the PMRPY and PMPRPY Schemes will be that are not to be paid by the employer will be shown separately.

PAY CHALLAN

  • The pay link will allow the employer to select the Bank through which he wants to pay.
  • Online payment is mandatory vide the notification dated 05.05.2015.
  • Offline payment is possible only in case the permission has been taken from the concerned PF Office.

IMPORTANT NOTE

Help files will be available for the following: Previous month Uploaded ECR txt file so that the employer can use the same in case there is less or no change and does not require to prepare ECR file again. Download of the Blank ECR file with the UANs and name so that the UAN is not required to be punched in for preparation of the ECR file. This will also be available for the Arrear file. The ECR format along with the additional data in the summary sheet will show that the ECR is having mainly three parts, namely Member Identifier, the Return and the Remittance details as follows:

Member Identifier: UAN: (The UAN should be linked with the establishment id and should not have : Date of joining later than the month for which the return is filed. Date of exit earlier than the month for which the return is filed. Name: Name even if differs from the name as per UAN Repository, then also the remittances made will be credited against the UAN.

Return Part:

For each employee:

  • Gross Wages
  •  EPF Wages
  • EPS Wages
  • EDLI Wages
  • NCP

For the establishment as a whole: (in the summary sheet

  • Number of employees in the month
  • Number of Excluded Employees out of above
  • Gross wages of the excluded employees.

Note: If the employer is paying the dues for any employee for the same month through more than one ECR (due to reasons such as part payment), he should declare the correct wages and NCP in all the files and part wages should not be shown. Similarly the employers uploading more than one ECR for a month should declare the same employee and excluded count etc in the multiple ECRs. In case of Arrear file the details of the employee, excluded employee and gross wages will not be asked.

Remittance Part

For each employees;

  • Employee share EPF
  • Pension Fund Contribution
  • Employer Share EPF
  • Refund of Advances

For the establishment as a whole:

  • EDLI Contribution
  • EPF Charges in A/c 2 (Administration and Inspection)
  • EDLI Charges in A/c 22 (Administration and Inspection)

FactoHR

FactoHR is complete solution to simplify your complicated payroll functions much easier.Automate your all HR processes for better informed,well organised, more responsive all while saving valuable time and money.Plan,apply and track your leave status online with FactoHR robust leave management software enabled with workflows